GE Aviation - Cardiff
Nationwide Asbestos Solutions Ltd were commissioned to undertake a programme of works for the removal and safe disposal for remaining asbestos insulating board, dura steel and full environmental clean of affected areas within test cell two and three as found in their asbestos report.
Due to previous historical issues on the project, and sensitivity regarding what could be done under what level of control we wanted to start our involvement in the project with a clear view of safety over all areas.
We wanted to ensure from the beginning that the channels of communication were open, and that all parties were satisfied with our control measures and techniques prior to mobilization on site.
Following consultation with our client and site management, our company director Tom Cox attended a number of site visits to make sure that a thorough review of the work was undertaken. Duration of work was estimated at 20 days, with all required equipment, removal team, and analysts commissioned by NAS to attend site.
Due to close liason with the client along with our ability to meet exacting requirements, we were able to avoid any unforeseen delays on site, and enable us to carry out the required asbestos work with as little further disruption as possible